Average Heritage doors/day per week (scheduled by ship date ÷ 5). Red dashed line = 8/day ceiling.
Per-date scheduled Heritage doors, and how many are already in the back. Red = over the 8/day ceiling.
| Ship date | Day | Doors | In back | Status |
|---|---|---|---|---|
| Oct 02 | Fri | 1 | — | LIGHT |
| Oct 06 | Tue | 4 | 4 | HEALTHY |
| Oct 07 | Wed | 3 | 3 | LIGHT |
| Oct 08 | Thu | 7 | 6 | HEALTHY |
| Oct 09 | Fri | 6 | 6 | HEALTHY |
| Oct 13 | Tue | 7 | 6 | HEALTHY |
| Oct 14 | Wed | 7 | 7 | HEALTHY |
| Oct 15 | Thu | 6 | 6 | HEALTHY |
| Oct 16 | Fri | 8 | 1 | HEALTHY |
| Oct 19 | Mon | 8 | — | HEALTHY |
| Oct 20 | Tue | 4 | — | HEALTHY |
| Oct 21 | Wed | 9 | — | OVERLOAD |
| Oct 22 | Thu | 8 | — | HEALTHY |
| Oct 23 | Fri | 8 | — | HEALTHY |
| Oct 26 | Mon | 3 | — | LIGHT |
| Oct 27 | Tue | 4 | — | HEALTHY |
| Oct 28 | Wed | 1 | — | LIGHT |
| Oct 29 | Thu | 6 | — | HEALTHY |
| Oct 30 | Fri | 5 | — | HEALTHY |
| Nov 02 | Mon | 1 | — | LIGHT |
| Nov 05 | Thu | 3 | — | LIGHT |
Estimated painted doors/day = (RI PAINT + 0.87 × RI PRODUCTION) ÷ 5 per week — mirrors your 'Painted Doors' column.
| Week of | Heritage/day | Status | Paint est./day | Status |
|---|---|---|---|---|
| Sep 21 | 0 | — | 0 | — |
| Sep 28 | 0.2 | LIGHT | 3.7 | LIGHT |
| Oct 05 | 4 | HEALTHY | 19.8 | OVERLOAD |
| Oct 12 | 5.6 | HEALTHY | 12.3 | HEALTHY |
| Oct 19 | 7.4 | HEALTHY | 13.6 | HEALTHY |
| Oct 26 | 3.8 | LIGHT | 5.9 | LIGHT |
| Nov 02 | 0.8 | LIGHT | 2.4 | LIGHT |
Total doors in each batch (from the Overview sheet). Total includes Oct 2 holding; Booked excludes it; the Oct 2 holding is split into Heritage vs other.
| Batch | Total | Booked | Oct 2 — Heritage | Oct 2 — other |
|---|---|---|---|---|
| RI SCHEDULE | 445 | 2 | 72 | 371 |
| RI TREE | 232 | 201 | 5 | 26 |
| RI PAINT | 142 | 141 | 0 | 2 |
| RI TRUCK | 132 | 125 | 0 | 7 |
| RI STOCK | 131 | 121 | 0 | 10 |
| RI FALSE TRIP | 28 | 13 | 2 | 13 |
| SUPPLY ONLY | 23 | 19 | 0 | 4 |
Parked on the Oct 2 holding date: demand with no firm ship date yet (not in the pipeline above) — shows what is coming.
| Heritage future demand — by category | Doors |
|---|---|
| RI SCHEDULE | 72 |
| RI SHOWHOME | 6 |
| RI 2026-09-24 | 1 |
By style: Catherine 31, Carmen 27, Jane 18, Other 3
Doors headed to Southern Alberta (Calgary, Airdrie, Cochrane, Chestermere, Strathmore, Balzac, Okotoks, High River) — from the Schedule tab, already-made & cancelled batches removed. Future = parked on the Oct 2 holding date (not yet booked); Booked = has a real ship date.
| By area | Heritage | Flush | Total |
|---|---|---|---|
| Calgary | 4 | 54 | 58 |
| Cochrane | 5 | 42 | 47 |
| Airdrie | 0 | 10 | 10 |
| Chestermere | 4 | 4 | 8 |
| Strathmore | 1 | 2 | 3 |
| Okotoks | 2 | 1 | 3 |
| High River | 0 | 1 | 1 |
| Balzac | 0 | 0 | 0 |